REMOVAL AND INSTALLATION
 
 
Pre-removal operation
  • Drive Belt Removal (Refer to GROUP 11A - Crankshaft Pulley ) <2.0L ENGINE>.
  • Drive Belt Removal (Refer to GROUP 11C - Crankshaft Pulley ) <2.4L ENGINE>.
Post-installation operation
  • Drive Belt Installation (Refer to GROUP 11A - Crankshaft Pulley ) <2.0L ENGINE>.
  • Drive Belt Installation (Refer to GROUP 11C - Crankshaft Pulley ) <2.4L ENGINE>.
  • Drive Belt Tension Check (Refer to GROUP 11A - On-vehicle Service, Drive Belt Tension Check ) <2.0L ENGINE>.
  • Drive Belt Tension Check (Refer to GROUP 11C - On-vehicle Service, Drive Belt Tension Check ) <2.4L ENGINE>.
Removal steps
1.Idler pulley
2.A/C compressor and clutch assembly connector
<<A>>>>C<<3.A/C compressor and clutch assembly
4.Generator connector
5.Generator terminal
>>B<<6.Grounding cable connection
<<B>>>>A<<7.Generator assembly
 
 
REMOVAL SERVICE POINTS
 
 
<<A>> A/C COMPRESSOR AND CLUTCH ASSEMBLY REMOVAL
1. Remove the A/C compressor and clutch assembly together with the hose from the bracket.
2. Tie the removed A/C compressor and clutch assembly with a string at a position where they will not interfere with the removal and installation of the generator assembly.
 

 
 
<<B>> GENERATOR ASSEMBLY REMOVAL
Remove the generator assembly to the downside.
 
 
 
INSTALLATION SERVICE POINTS
 
 
>>A<< GENERATOR ASSEMBLY INSTALLATION
For the installation procedure, refer to GROUP 11B - Generator and Ignition System <2.0L ENGINE> or refer to GROUP 11D - Generator and Ignition System <2.4L ENGINE>.
 

 
 
>>B<< GROUNDING CABLE CONNECTION
Install the grounding cable within the area marked with A in the illustration.
 

 
 
>>C<< A/C COMPRESSOR AND CLUTCH ASSEMBLY INSTALLATION
Tighten A/C compressor and clutch assembly mounting bolts to the specified torque in the order of number shown in the illustration.
Tightening torque: 23 ± 6 N·m (17 ± 4 ft-lb)