REMOVAL AND INSTALLATION
 
 
Removal steps
1.Propeller shaft assembly (Refer to GROUP 25 - Propeller Shaft ).
2.Cover
3.Breather hose connection
4.Connector connection
5.Bracket
>>A<<6.Electronic control coupling
7.Wave washer
 
 
INSTALLATION SERVICE POINT
 
 
>>A<< ELECTRONIC CONTROL COUPLING INSTALLATION
1. Check that the length of the electronic control coupling stud bolt (A) is within the standard value range.
Standard value: 21.6 - 24.4 mm (0.86 - 0.96 inch)
2. If it exceeds either of the limits, clean the threads for the electronic control coupling and replace the stud bolt.
Tightening torque: 13 ± 2 N·m (115 ± 17 in-lb)