Inspection
INSPECTION AFTER REMOVAL
Check the following items, and replace the parts if necessary.
Transverse Link
Transverse link for deformation, cracks or damage.
Check the bushing for complete separation. (If completely separated, inner metal can be pulled out from transverse link.)
Ball joint boot for cracks or other damage, and also for grease leakage.
Swing Torque
1.
Manually move ball stud to confirm it moves smoothly with no binding.
2.
Move ball stud at least ten times by hand to check for smooth movement.
3.
Hook a spring scale (A) at cutout on ball stud
. Confirm spring scale measurement value is within specifications when ball stud begins moving.
Swing torque
: Refer to Ball Joint
Ball Joint
.
Measurement on spring scale
: Refer to Ball Joint
Ball Joint
.
If swing torque exceeds standard range, replace transverse link assembly.
Axial End Play
1.
Move ball stud at least ten times by hand to check for smooth movement.
2.
Move tip of ball stud in axial direction to check for looseness.
If there is axial end play, replace transverse link assembly.
INSPECTION AFTER INSTALLATION
1.
Check wheel alignment. Refer to
Inspection
.
2.
Adjust neutral position of steering angle sensor. Refer to Description
Description
.